Vinton Construction

2018 CTH B and USH 41 Interchange, Suamico

Wisconsin Department of Transportation

http://bt9.lancellottiforniture.com/images/2018%20CTH%20B%20and%2041%20Interchange/_projectHero/IMG_0031.JPG

Date Completed:

November 2018

Services:

Concrete Pavement, Earthwork & Grading, Underground Utilities, Custom Crushing

Design Engineer:

KL Engineering

Construction Engineer:

Wisconsin Department of Transportation

Project Summary:

Vinton Construction was a subcontractor on the CTH B and USH 41 interchange reconstruction from the North bound ramps to Velp Ave. USH 41 was brought up to Federal Highway standards with slope corrections of the medians for approximately 12 miles from Lineville Rd. to Oconto.

Contract Amount:

$17,958,809.00

Project Length:

12 Miles

By the Numbers:

  • 15,700 SY of 8-inch Concrete Pavement
  • 5300 SY of Removing Concrete Pavement
  • 29631 CY of Common Excavation
  • 25464 CY of Borrow
  • 38000 Tons of Base Aggregate
  • 6500 LF of Concrete Curb and Gutter
  • 38000 SF of Concrete Sidewalk
  • 1400 LF of Storm Sewer
  • 168,000 SY of Salvaged Topsoil
  • 48 Sewer Structures
IMG_0038
IMG_1435
IMG_1444
IMG_0127
IMG_1493
IMG_1513
IMG_1669
IMG_2005
IMG_1647
IMG_1416
IMG_0029
IMG_1084
IMG_1102
IMG_1689
IMG_0054
IMG_1128
IMG_0344
IMG_0457
IMG_1652
IMG_1651